PROJECT TIMELINE

  • Planning

  • A​rchi​tect appointed

  • Bu​ilder Appointed

    Q4, 2017

  • Construction Commenced

    Q4, 2017

  • Construction Complete

    Q1, 2018

Quarters are based on the calendar year.​

​​