​​​​Boronia Heights Primary School received funding in the 2017-18 State Budget to complete Stage 2 works of the modernisation project.

The funding this school received in the 2014-15 and 2015-16 State Budgets has been rolled into one project to complete a major modernisation of the school. Two of the main buildings will be upgraded to create flexible learning environments, new students toilets and staff administration areas. The existing hall will be demolished and replaced with a new gym and performing arts facilities.

​This project is an election commitment for the Victorian Government

architect

The architects for this​ project are Mal Ta​​ylor Architect​.​

builder

Adma Group has been appointed as the builder for this project.

​​​PROJECT TIMELINE
​​
  • ARCHITECT
    ​APPO​​INTED

  • BUILD​ER APPOINT​ED

  •  

    CONSTRUCTION COMM​​​ENCES

    Q1, 2017

  •  

    BUILDING OPEN

    Q4, 2017

The below quarters are forecasted only and subject to change dependant on future budget decisions and other varying factors. These quarters are based on the calendar year.​​​​​​​​​​​​​​​​​​​​​​​​​


For interpretation services, please ring the Victorian School Building Authority language line on 03 9280 0712