​We have completed designing this project and appointed a builder to replace the relocatable building with new classrooms, and refurbish and upgrade other buildings.

ARCHITECT

The architect is ​Henderson + Lodge Architects​.​​

BUILDER

The builder is WM Flynn Pty Ltd.

FACILITIES

After replacing the relocatable with permanent classrooms, we will undertake minor works around the school including upgrading the administration area, adding and refurbishing student and staff toilets, extending the multipurpose room and landscaping and decking the courtyard.

Project d​​ocuments

​​

​​ ​PROJECT TIMELINE
​​
  • ARCHITECT
    ​APPO​​INTED

  • DESIGN

  •  

    BUILDER APPOINTED

    Q2, 2017

  • CONSTRUCTION COMMENCES

    Q2, 2017

  •  

    BUILDING OPEN

    Q2, 2018

The above dates are forecasted only and subject to change.​​​​​​​​​​​​​​​​​​​​​​​​​


For interpretation services, please ring the Victorian School Building Authority language line on 03 9280 0712

Contact us

33 St Andrews Place
East Melbourne
VIC 3002

Email: vsba@edumail.vic.gov.au
Phone: 1800 896 950