Box Hill High School

Location
1180 Whitehorse Rd Box Hill 3128

Minor Capital Works Fund

  • Start

    Q2 2022
  • Planning

  • Design

  • Construction

  • Finish

    Q2 2024

The above dates are forecast only and subject to change.

About the project

We are undertaking a partial refurbishment of the existing accessible toilet and shower in the school's gymnasium to improve amenity, accessibility and hygiene. This work is supported by our Minor Capital Works Fund – a program for small building projects that make a big difference in our schools.

Funding

In the 2022–23 State Budget the project received $115,627 from the Minor Capital Works Fund.

Funding type

  • Minor Capital Works Fund

Minor Capital Works Fund

  • Start

    Q4 2020
  • Planning

  • Design

  • Construction

  • Finish

    Q3 2023

The above dates are forecast only and subject to change.

About the project

We upgraded the toilet blocks to improve amenity, cleanliness and hygiene.

Funding

In the 2020 Minor Capital Works Fund, the school was allocated $500,000.

Funding type

  • Minor Capital Works Fund

Upgrade and Modernisation

  • Start

    Q2 2018
  • Planning

  • Design

  • Construction

  • Finish

    Q4 2019

The above dates are forecast only and subject to change.

About the project

We refurbished the Junior Science Classrooms at Box Hill High School.

Funding

In the 2018–19 State Budget $500,000 was allocated to the school.

Funding type

  • Upgrade and Modernisation

Updated