- 38 Raleigh Street Essendon 3040
Upgrade and Modernisation – hardcourts
Start
Q2 2023Planning
Design
Construction
Finish
Q2 2026
The above dates are forecast only and subject to change.
About the project
We are replacing the asphalt hardcourts with a new rubberised surface. We are also upgrading the active and nature play areas and the assembly area, as well as completing landscaping works.
Funding
In the 2023-24 State Budget the school shared in $24 million allocated for planning. In the 2024-25 State Budget, total project funding of $2.6 million was announced.
Funding type
- Upgrade and Modernisation
Upgrade and Modernisation
Start
Planning
Design
Construction
Finish
Q4 2018
The above dates are forecast only and subject to change.
About the project
We built a new administration and senior primary learning neighbourhood. We also refurbished existing buildings, including Block A and Block B.
Funding
In the 2014–15 State Budget, $4.979 million was allocated to this project. In the 2017–18 State Budget, an additional $766,000 was allocated to this project. The school also received $62,000 in Planned Maintenance Program Funding.
Funding type
- Upgrade and Modernisation
Updated