- 150 High St Broadford 3658
Building Blocks Capacity Grant - Expansion
Start
Q2 2022Planning
Design
Construction
Finish
Q1 2024
The above dates are forecast only and subject to change.
About the project
We added another kindergarten room to the centre. This allows the centre to offer 33 additional places as part of the roll-out of funded kindergarten for 3-year-olds, giving more local children 2 years of high-quality education.
Funding
In Round 2 of the 2021–22 Building Blocks Capacity Grant, $1,763,000 was allocated to this project.
Funding type
- Building Blocks Capacity Grant
Early Learning Facility Upgrade
Start
Planning
Design
Construction
Finish
Q4 2017
The above dates are forecast only and subject to change.
About the project
Mitchell Shire Council upgraded Mt Piper Kindergarten (now Mt Piper Broadford Family and Children’s Centre) to include two new multipurpose consulting rooms, a waiting area, shared group space, kitchenette facilities, and a centre entrance to the kinder rooms.
The additional spaces will enable group sessions to be more conducted, and will provide a more direct and suitable entrance to the kindergarten rooms.
Funding
In 2015–16, $350,000 was allocated to the kindergarten.
Funding type
- Early Learning Facility Upgrade
Updated