Location
8–10 Fraser Street Rochester 3561
Early Childhood Refurbishment and Minor Works
-
Start
Q3 2021
-
Planning
-
Design
-
Construction
-
Finish
Q4 2023
The above dates are forecast only and subject to change.
About the project
We are upgrading the appearance and functionality of Shine Bright Rochester Kindergarten.
We are installing a new sink for the children and connecting hot water to the main room. We’ll replace deteriorating floor coverings, and repaint the inside and outside of the centre.
Funding
In Round 1 of the 2021-22 Early Childhood Refurbishment and Minor Works Program, $54,677 was allocated to this project.
Funding type
Early Childhood Refurbishment and Minor Works
Reviewed 03 February 2022