Location
16 Sharpes Rd Watsonia North 3087
Upgrade and Modernisation
-
Start
Q2 2021
-
Planning
-
Design
-
Construction
-
Finish
Q2 2024
The above dates are forecast only and subject to change.
About the project
We are upgrading and modernising the school, including:
- building a permanent school building
- minor window repairs to blocks A and B.
This ensures students are learning in an environment designed for delivering modern education.
Funding
In the 2021–22 State Budget, the school received $4.719 million. In 2022 the school was allocated a further $214,991.
Funding type
Upgrade and Modernisation
Minor Capital Works Fund
-
Start
Q4 2023
-
Planning
-
Design
-
Construction
-
Finish
Q4 2025
The above dates are forecast only and subject to change.
About the project
We are refurbishing the school's Building A classrooms. Our Minor Capital Works Fund is supporting this work. It provides grants for small building projects that make a big difference in our schools.
Funding
In the 2023-24 State Budget the project received $498,960 from the Minor Capital Works Fund.
Funding type
Minor Capital Works Fund
Reviewed 30 November 2023