Location
50 Vannam Dr Ashwood 3147
Upgrade and Modernisation
-
Start
Q2 2020
-
Planning
-
Design
-
Construction
-
Finish
Q4 2023
The above dates are forecast only and subject to change.
About the project
We are upgrading and modernising this school, including building a new school entrance and improving access to the netball car park.
Funding
From the 2020–21 Infrastructure Planning and Acceleration fund, the school was allocated $552,200 in planning funding.
In the 2020–21 State Budget, the school received $9.742 million.
Funding type
Upgrade and Modernisation
Reviewed 17 October 2022