Location
118 Barnett St Avoca 3467
Upgrade and Modernisation
-
Start
Q2 2019
-
Planning
-
Design
-
Construction
-
Finish
Q3 2020
The above dates are forecast only and subject to change.
About the project
We upgraded the school's basketball court and refurbished the floorboards in 2 classrooms.
Funding
In the 2019–20 State Budget, the school received $300,000.
Funding type
Upgrade and Modernisation
Minor Capital Works Fund - Round 2
-
Start
Q4 2021
-
Planning
-
Design
-
Construction
-
Finish
Q3 2023
The above dates are forecast only and subject to change.
About the project
We repaired the roof, replaced windows, and repainted the heritage building's facade.
Funding
In Round 2 of the Minor Capital Works Fund, the project received $229,298.
Funding type
Minor Capital Works Fund
Reviewed 23 August 2023