Location
79-99 Dalgetty Rd Beaumaris 3193
Permanent Modular School Buildings Program
-
Start
Q2 2018
-
Planning
-
Design
-
Construction
-
Finish
Q2 2019
The above dates are forecast only and subject to change.
About the project
We delivered a new architect-designed modular building to the school to replace Block C.
Funding
In Round 3 of the program, the school was allocated $2,644,000.
Funding type
Permanent Modular School Buildings Program
Minor Capital Works Fund
-
Start
Q4 2020
-
Planning
-
Design
-
Construction
-
Finish
Q1 2023
The above dates are forecast only and subject to change.
About the project
We resurfaced the oval and basketball courts with a synthetic surface. The works improve the outdoor learning environment and condition of the school.
Funding
In the 2020 Minor Capital Works Fund, the school was allocated $321,125.
Funding type
Minor Capital Works Fund
Reviewed 17 April 2023