Bellbrae Primary School

Location
50 School Rd Bellbrae 3228

Inclusive Schools Fund – Round 8

  • Start

    Q4 2022
  • Planning

  • Design

  • Construction

  • Finish

    Q2 2024

The above dates are forecast only and subject to change.

About the project

We are building an outdoor inclusive learning space. It will give children of all abilities new ways to socialise, develop and learn through play.

Funding

In Round 8 of the Inclusive Schools Fund, the project received $200,000.

Funding type

  • Inclusive Schools Fund

Upgrade and Modernisation - gym, learning spaces, science, technology, engineering and maths facilities

  • Start

    Q2 2019
  • Planning

  • Design

  • Construction

  • Finish

    Q1 2023

The above dates are forecast only and subject to change.

About the project

We modernised Bellbrae Primary with a competition-grade gym, open learning spaces and new science, technology, engineering and maths facilities. We also made improvements to the school oval.

Funding

In the 2019–20 State Budget, the school received $9.1 million.

Funding type

  • Upgrade and Modernisation

Upgrade and Modernisation - water and sewerage works

  • Start

  • Planning

  • Design

  • Construction

  • Finish

    Q2 2022

The above dates are forecast only and subject to change.

About the project

​​We funded this project, delivered by the water authority, to provide the school with permanent sewer and town water connections.

Funding

In 2020, the school received $2.38 million for these works.

Funding type

  • Upgrade and Modernisation

Upgrade and Modernisation - amenities block

  • Start

  • Planning

  • Design

  • Construction

  • Finish

    Q3 2019

The above dates are forecast only and subject to change.

About the project

We refurbished the amenities block at Bellbrae Primary School. 

Funding

In the 2017-18 State Budget, $754,000 was allocated to the school.

Funding type

  • Upgrade and Modernisation

Updated