Belmont High School

Location
Rotherham St Belmont 3216

Upgrade and Modernisation – science and learning building

  • Start

    Q2 2023
  • Planning

  • Design

  • Construction

  • Finish

    Q3 2027

The above dates are forecast only and subject to change.

About the project

We are building a new science and learning building. This will give students more modern learning spaces.

Funding

In the 2023–24 State Budget the school shared in $24 million allocated for planning. The 2025–26 State Budget announced total project funding of $11.2 million. This includes earlier planning funding.

Funding type

  • Upgrade and Modernisation

Upgrade and Modernisation

  • Start

    Q4 2017
  • Planning

  • Design

  • Construction

  • Finish

    Q1 2019

The above dates are forecast only and subject to change.

About the project

We completed the first stage of modernising Belmont High School.

Stage one works include:

  • creating a new performing arts facility with a flexible 290-seat theatre space, bio-box and adjoining music and drama rooms
  • a new entry foyer, toilets, canteen and covered eating area with café style kiosk
  • new change rooms for the gymnasium
  • upper level multi-purpose teaching space with access to an outdoor learning deck
  • new staff planning space, staff shower and change facilities
  • internal painting of the art and technology wing.

This project was a finalist in the 2019 Victorian School Design Awards.

Funding

In the 2016–17 State Budget, $5.24 million has been allocated to the school.

Funding type

  • Upgrade and Modernisation

Updated