Location
26-32 Lockwood Rd Kangaroo Flat 3555
Upgrade and Modernisation
-
Start
Q2 2022
-
Planning
-
Design
-
Construction
-
Finish
Q4 2025
The above dates are forecast only and subject to change.
About the project
We are modernising the school to give students better learning opportunities. In this significant upgrade, we will build new classrooms and learning spaces.
Funding
In the 2022–23 State Budget, this school received at least $8.874 million.
Funding type
Upgrade and Modernisation
Minor Capital Works Fund
-
Start
Q4 2020
-
Planning
-
Design
-
Construction
-
Finish
Q2 2025
The above dates are forecast only and subject to change.
About the project
We are developing an outdoor health and physical education hub.
Funding
In the 2020 Minor Capital Works Fund, the school was allocated $303,125.
Funding type
Minor Capital Works Fund
Inclusive Schools Fund
-
Start
Q4 2018
-
Planning
-
Design
-
Construction
-
Finish
Q2 2020
The above dates are forecast only and subject to change.
About the project
We built a sensory space and accessible playground (including unrestricted access for students with vision impairments) offering a range of movement experiences (e.g. climbing, bouncing, rocking, running and crawling) and opportunities for sensory exploration.
Funding
In 2018, $171,000 was allocated to the school in Round 4 of the Inclusive Schools Fund.
Funding type
Inclusive Schools Fund
Reviewed 08 December 2022