Location
Cnr Fawthrop & Edgar St Portland 3305
Inclusive Schools Fund - Round 6
-
Start
Q2 2021
-
Planning
-
Design
-
Construction
-
Finish
Q1 2023
The above dates are forecast only and subject to change.
About the project
We are building an outdoor inclusive learning space in a landscaped environment, including a yarning circle.
Funding
In Round 6 of the Inclusive Schools Fund, this project received $200,000.
Funding type
Inclusive Schools Fund
Inclusive Schools Fund - Round 4
-
Start
Q4 2018
-
Planning
-
Design
-
Construction
-
Finish
Q3 2019
The above dates are forecast only and subject to change.
About the project
We built a sensory play space, with musical activities, sand and water play, an access spinner, roller table, rockin’ robin (i.e. an egg chair) and visual stimuli that will continue to improve the curriculum for children with special needs.
Funding
In 2018, $164,000 was allocated to the school in Round 4 of the Inclusive Schools Fund.
Funding type
Inclusive Schools Fund
Reviewed 29 September 2022