Location
Barkly St Bendigo 3550
Non-Government Schools Capital Fund
-
Start
Q3 2017
-
Planning
-
Design
-
Construction
-
Finish
Q1 2019
The above dates are forecast only and subject to change.
About the project
We supported the school to upgrade the Coolock campus in Junortoun (St Vincents Road ). The project involved demolishing existing buildings and constructing 14 general learning areas and associated amenities.
The school contributed funds to the project, which cost a total of $9 million.
Funding
As part of the 2015–16 to 2018–19 Capital Funding Program for Non-Government Schools, $1 million has been allocated to the school.
Funding type
Non-Government Schools Capital Fund