Location
117-125 Cleeland St Dandenong 3175
Upgrade and Modernisation
-
Start
Q2 2021
-
Planning
-
Design
-
Construction
-
Finish
Q1 2023
The above dates are forecast only and subject to change.
About the project
We built a competition-grade gymnasium, with a canteen and music room. We converted the existing gymnasium into a library and project space for Science, Technology, Engineering and Maths (STEM).
Funding
In the 2021–22 State Budget, the school received $6 million, to combine with a $2 million co-contribution from the school.
Funding type
Upgrade and Modernisation
Permanent Modular School Buildings Program
-
Start
-
Planning
-
Design
-
Construction
-
Finish
Q4 2018
The above dates are forecast only and subject to change.
About the project
We built a new architect-designed modular building for the school to replace Block B. This offers new classrooms and toilet facilities.
Funding
In the 2017–18 State Budget, $1,914,000 was allocated to the school as part of the Permanent Modular School Buildings Program.
Previously $148,000 Planned maintenance funding was allocated to address site infrastructure.
Funding type
Permanent Modular School Buildings Program
Reviewed 17 May 2023