Gladstone Park Primary School

Location
15 - 25 South Circular Road Gladstone Park 3043

Upgrade and Modernisation - Block B

  • Start

    Q2 2019
  • Planning

  • Design

  • Construction

  • Finish

    Q4 2021

The above dates are forecast only and subject to change.

About the project

We built a new single level neighbourhood cluster with four classrooms, teacher work spaces, withdrawal spaces and learning resources storage. This replaced older facilities, ensuring that students learn in facilities designed for modern education.

Funding

In the 2019-20 State Budget, the school received $252,400. In 2020, the school received $2.27 million.

Funding type

  • Upgrade and Modernisation

Upgrade and Modernisation

  • Start

    Q2 2018
  • Planning

  • Design

  • Construction

  • Finish

    Q3 2020

The above dates are forecast only and subject to change.

About the project

We upgraded and modernised facilities at Gladstone Park Primary School, including constructing a new learning neighborhood consisting of classrooms, teacher work spaces and withdrawal spaces.   

Funding

In the 2018-19 State Budget $1.5 million was allocated to the school.

Funding type

  • Upgrade and Modernisation

Updated