- 14 - 36 Taylor Drive Gladstone Park 3043
Upgrade and Modernisation
Start
Q2 2023Planning
Design
Construction
Finish
Q1 2027
The above dates are forecast only and subject to change.
About the project
We're upgrading and modernising this school to give students better learning spaces. This includes:
- refurbishing the C Block and Senior Block
- landscaping the perimeter of C Block and Senior Block, including the area next to the canteen
- removing 2 modular buildings
- building a new student toilet and locker bay
- improving the T Block Textiles and Visual Arts classrooms.
Funding
In the 2023-24 State Budget the school shared in $24 million allocated for planning. In the 2024-25 State Budget, total project funding of $11.7 million was announced.
Funding type
- Upgrade and Modernisation
Updated