Start
Q4 2020
-
Planning
-
Design
-
Construction
-
Finish
Q3 2023
The above dates are forecast only and subject to change.
About the project
We are building a new VCE centre for the school.
Funding
In the 2020–21 State Budget, the school received $3.295 million.
Funding type
Upgrade and Modernisation
Upgrade and Modernisation, Shared Facilities Fund
-
Start
-
Planning
-
Design
-
Construction
-
Finish
Q4 2018
The above dates are forecast only and subject to change.
About the project
We built a synthetic soccer pitch with floodlighting and car parking .
Funding
This school received $415,000 from the Shared Facilities Fund. This school also received $502,000 in the 2017–18 State Budget.