Location
Cairnbrook Rd Glengarry 3854
Minor Capital Works Fund - Round 2
-
Start
Q4 2021
-
Planning
-
Design
-
Construction
-
Finish
Q3 2023
The above dates are forecast only and subject to change.
About the project
We refurbished the student and staff bathrooms to improve amenity, cleanliness and hygiene.
Funding
In Round 2 of the Minor Capital Works Fund, the project received $499,674.
Funding type
Minor Capital Works Fund
Minor Capital Works Fund
-
Start
Q4 2020
-
Planning
-
Design
-
Construction
-
Finish
Q4 2021
The above dates are forecast only and subject to change.
About the project
We helped the school with landscaping that improves the functionality and appeal of several under-utilised areas across the school grounds.
Funding
In the 2020 Minor Capital Works Fund the school was allocated $160,165.
Funding type
Minor Capital Works Fund
Inclusive Schools Fund – Round 8
-
Start
Q4 2022
-
Planning
-
Design
-
Construction
-
Finish
Q1 2024
The above dates are forecast only and subject to change.
About the project
We are building an outdoor inclusive learning space. It will give children of all abilities new ways to socialise, develop and learn through play.
Funding
In Round 8 of the Inclusive Schools Fund, the project received $188,840.
Funding type
Inclusive Schools Fund
Reviewed 11 September 2023