Upgrade and Modernisation - Next Stage
-
Start
Q4 2020
-
Planning
-
Design
-
Construction
-
Finish
Q2 2023
The above dates are forecast only and subject to change.
About the project
We added a performing arts centre (for music and drama), as well as a canteen to the school’s gymnasium building. We also built a car park.
We talked with school leaders to ensure works would help achieve educational goals. We ensured that improvements targeted areas that required them most.
Funding
In the 2020–21 State Budget, the school received $2.5 million.
Funding type
Upgrade and Modernisation
Upgrade and Modernisation
-
Start
Q2 2018
-
Planning
-
Design
-
Construction
-
Finish
Q1 2021
The above dates are forecast only and subject to change.
About the project
We upgraded facilities at the school, including a new competition grade gym. We also refurbished the HOPE centre, which provides student wellbeing and counselling services.
Funding
In the 2018–19 State Budget $5.5 million was allocated to the school.
Funding type
Upgrade and Modernisation
Inclusive Schools Fund
-
Start
Q4 2018
-
Planning
-
Design
-
Construction
-
Finish
Q1 2020
The above dates are forecast only and subject to change.
About the project
We helped build a flexible space to encourage collaboration, as well as an area to support learning in science, engineering and maths. New connecting doors lead to an outdoor area.
Funding
In 2018, $150,000 was allocated to the school in Round 4 of the Inclusive Schools Fund.
Funding type
Inclusive Schools Fund