Helm Street Kindergarten

Location
13 Helm St Kangaroo Flat 3555

Early Childhood Refurbishment and Minor Works

  • Start

    Q1 2022
  • Planning

  • Design

  • Construction

  • Finish

    Q1 2023

The above dates are forecast only and subject to change.

About the project

We refurbished Shine Bright Helm Street Kindergarten.

The works included:

  • replacing flooring,
  • repainting,
  • upgrading the art cubby house,
  • renovating the bathroom, and
  • resurfacing the carpark.

Funding

In Round 1 of the 2021 Early Childhood Refurbishment and Minor Works grant, $119,190 was allocated to this project.

Funding type

  • Early Childhood Refurbishment and Minor Works

Updated