Upgrade and Modernisation

  • Start

    Q2 2022
  • Planning

  • Design

  • Construction

  • Finish

    Q4 2024

The above dates are forecast only and subject to change.

About the project

We are constructing a new junior learning building at Kambrya College. The new building has:
  • 16 flexible classrooms
  • break out spaces
  • a connection to outdoor learning areas
  • staff facilities
The design encourages collaboration between staff and students, and there will be a multipurpose area available for community use.

Funding

In the 2022–23 State Budget, this school received at least $18.945 million.

Funding type

  • Upgrade and Modernisation

Kambrya College - indicative site plan

  • Download' Kambrya College - indicative site plan'

Upgrade and Modernisation

  • Start

  • Planning

  • Design

  • Construction

  • Finish

    Q3 2018

The above dates are forecast only and subject to change.

About the project

We built a new senior learning block​ at Kambrya College.  The new building has nine flexible classrooms, break out spaces, a connection to outdoor learning areas and staff facilities.  ​The building has been designed to encourage collaboration between staff and students and also has a multipurpose area available for community use.

Funding

In the 2016-17 State Budget, $3 million was allocated to the school.

Funding type

  • Upgrade and Modernisation