Location
1-9 Epping St Kyneton 3444
Upgrade and Modernisation - Next Stage
-
Start
Q4 2020
-
Planning
-
Design
-
Construction
-
Finish
Q3 2023
The above dates are forecast only and subject to change.
About the project
We are continuing to upgrade the school. These latest works will include upgrading Block J and building a new STEAM building.
Funding
In the 2020–21 State Budget, the school received $10.991 million.
Funding type
Upgrade and Modernisation
Upgrade and Modernisation
-
Start
Q4 2017
-
Planning
-
Design
-
Construction
-
Finish
Q2 2019
The above dates are forecast only and subject to change.
About the project
We have upgraded the school by repurposing numerous buildings. We created a new Year 7 and 8 Learning Centre, with flexible learning environments, as well as a vocational education and training hub.
We have rebuilt Kyneton Primary School next door, to form an education precinct.
Facilities
We built the Training and Innovation Hub, which will provide innovative learning spaces, including hands-on workshops.
Funding
A total of $10.9 million was allocated to this project.
Funding type
Upgrade and Modernisation
Reviewed 11 November 2022