Macleod College

Location
Carwarp Street Macleod 3085

Upgrade and Modernisation

  • Start

    Q2 2019
  • Planning

  • Design

  • Construction

  • Finish

    Q2 2022

The above dates are forecast only and subject to change.

About the project

We built a new science building, created new primary school play areas and completed entry landscaping. We also demolished older buildings and facilities that were no longer needed.

Funding

In the 2019–20 State Budget, the school received $492,900. In 2020, the school received $4.44 million.

Funding type

  • Upgrade and Modernisation

School Improvement Fund

  • Start

  • Planning

  • Design

  • Construction

  • Finish

The above dates are forecast only and subject to change.

About the project

We converted the tennis courts into a meditation garden.​​​​​​  ​

Funding

In the 2015–16 State Budget, $5,000 was allocated to the school.

Funding type

  • School Improvement Fund