Mount Clear College

Location
59 Olympic Avenue Mount Clear 3353

Upgrade and Modernisation - Stage 1

  • Start

    Q2 2016
  • Planning

  • Design

  • Construction

  • Finish

    Q4 2018

The above dates are forecast only and subject to change.

About the project

This project delivered a central technical hub, reconfigured from the south end of Building C, as well as created flexible learning spaces. We also improved the building's energy efficiency.​

Funding

In the 2016–17 State Budget, $2.1 million was allocated to the school.

Funding type

  • Upgrade and Modernisation

Upgrade and Modernisation - Stage 2

  • Start

    Q2 2018
  • Planning

  • Design

  • Construction

  • Finish

    Q3 2020

The above dates are forecast only and subject to change.

About the project

Stage 2 upgrades are now complete. We have refurbished the ground floor of Block B to:​

  • create arts and science hubs, VCAL areas, Year 10, 11 and 12 study areas and related staff areas
  • replace external fabric and windows and doors.

Funding

This project was allocated $3 million in the 2018-19 State Budget.

Funding type

  • Upgrade and Modernisation

Upgrade and Modernisation - Stage 3

  • Start

    Q2 2019
  • Planning

  • Design

  • Construction

  • Finish

    Q2 2021

The above dates are forecast only and subject to change.

About the project

We upgraded Mount Clear College. The latest funding was used to modernise Block A, which houses the food technology, music, drama and science facilities.

Funding

In the 2019-20 State Budget, the school received $5.5 million.

Funding type

  • Upgrade and Modernisation

Updated