Location
59 Olympic Avenue Mount Clear 3353
Upgrade and Modernisation - Stage 1
-
Start
Q2 2016
-
Planning
-
Design
-
Construction
-
Finish
Q4 2018
The above dates are forecast only and subject to change.
About the project
This project delivered a central technical hub, reconfigured from the south end of Building C, as well as created flexible learning spaces. We also improved the building's energy efficiency.
Funding
In the 2016–17 State Budget, $2.1 million was allocated to the school.
Funding type
Upgrade and Modernisation
Upgrade and Modernisation - Stage 2
-
Start
Q2 2018
-
Planning
-
Design
-
Construction
-
Finish
Q3 2020
The above dates are forecast only and subject to change.
About the project
Stage 2 upgrades are now complete. We have refurbished the ground floor of Block B to:
- create arts and science hubs, VCAL areas, Year 10, 11 and 12 study areas and related staff areas
- replace external fabric and windows and doors.
Funding
This project was allocated $3 million in the 2018-19 State Budget.
Funding type
Upgrade and Modernisation
Upgrade and Modernisation - Stage 3
-
Start
Q2 2019
-
Planning
-
Design
-
Construction
-
Finish
Q2 2021
The above dates are forecast only and subject to change.
About the project
We upgraded Mount Clear College. The latest funding was used to modernise Block A, which houses the food technology, music, drama and science facilities.
Funding
In the 2019-20 State Budget, the school received $5.5 million.
Funding type
Upgrade and Modernisation
Reviewed 07 October 2022