Upgrade and Modernisation - Next Stage
-
Start
Q2 2020
-
Planning
-
Design
-
Construction
-
Finish
Q2 2023
About the project
From the 2020–21 Infrastructure Planning and Acceleration fund, the school was allocated $820,000 in planning funding. In the 2020–21 State Budget, the school received $7.38 million.
Permanent Modular School Buildings Program
-
Start
Q2 2018
-
Planning
-
Design
-
Construction
-
Finish
Q2 2019
About the project
We delivered a new architect-designed modular building to Norwood Secondary College. To do this we demolished Block A and replaced it with a Science Building.
Our modular facilities require less time for planning and construction, resulting in reduced disruption to students, staff and teaching programs. They are sustainable and innovatively designed, with a comparable lifespan to bricks and mortar structures. Norwood Secondary College is benefitting from the Permanent Modular School Buil dings Program .
Upgrade and Modernisation
-
Start
-
Planning
-
Design
-
Construction
-
Finish
Q4 2018
About the project
We built a new stadium at Norwood Secondary College, including a new competition-grade basket ball court and additional single court complex.
The Maroondah Education Plan includes the stadium for Norwood Secondary College, a performing arts centre for Mullum Primary School, a redevelopment for Ringwood Secondary College, and consolidation of Melba College's two campuses onto one site.
In the 2015–16 State Budget, $3.7 million was allocated to the school. The school also received $750,000 in School Pride and Sports Funding.
Reviewed 28 October 2022