Quarry Hill Primary School

Location
25 Peel Street Quarry Hill 3550

Minor Capital Works Fund - Round 2

  • Start

    Q4 2021
  • Planning

  • Design

  • Construction

  • Finish

    Q4 2023

The above dates are forecast only and subject to change.

About the project

We replaced the student amenities block. It has improved amenity, cleanliness and hygiene.

Funding

In Round 2 of the Minor Capital Works Fund, the project received $499,637

Funding type

  • Minor Capital Works Fund

Inclusive Schools Fund

  • Start

  • Planning

  • Design

  • Construction

  • Finish

The above dates are forecast only and subject to change.

About the project

We built a dedicated outdoor sensory learning space. It provides a variety of sensory experiences and safe spaces for vulnerable students.

The space includes:

  • log seating and climbing area under a multi-coloured glazed roof,
  • concrete vertical half-pipes to allow chalk drawings and textured surfaces,
  • a small bean cubby,
  • and a raised platform for group art work.

The new space will also allow staff to extend their professional learning for practical outcomes.

Funding

In Round 2 of the Inclusive Schools Fund, $97,000 was allocated to the school.

Funding type

  • Inclusive Schools Fund

Updated