340 Settlement Rd Sunbury 3429

Building Fund for Non-Government Schools – Independent

  • Start

    Q4 2024
  • Planning

  • Design

  • Construction

  • Finish

    Q2 2026

The above dates are forecast only and subject to change.

About the project

We are helping the school build a 2-storey modular building. It will include administration offices, a first aid room and a small library. There will also be toilets, a kitchen area and a meeting room for staff.

Funding

In Round 2 of the Building Fund for Non-Government Schools – Independent, the school received $2.4 million.

Funding type

  • Building Fund for Non-Government Schools

Non-Government Schools Capital Fund – 2021–22

  • Start

    Q3 2021
  • Planning

  • Design

  • Construction

  • Finish

    Q2 2023

The above dates are forecast only and subject to change.

About the project

We helped the school demolish their Prep–Year 2 classrooms and build a new building. It now has 3 general learning areas, staff workspaces, a small group space, storage, and toilets. We also upgraded the septic system, and added landscaping and new play areas.

Funding

Under the 2021–22 capital funding program for non-government schools, the school received $1.5 million.

Funding type

  • Non-Government Schools Capital Fund