Location
43 Paxton St South Kingsville 3015
Building Blocks Improvement Grant – Play Space
-
Start
Q4 2021
-
Planning
-
Design
-
Construction
-
Finish
Q2 2023
The above dates are forecast only and subject to change.
About the project
We built a multi-sensory, inclusive play and learning space inspired by Indigenous themes.
The space is designed to encourage children to engage calmly with nature and each other.
Funding
In Round 1 of the 2020-2021 Building Blocks Improvement Grant, $176,896 was allocated to this project.
Funding type
Building Blocks Improvement Grant
Building Blocks Improvement Grant
-
Start
Q4 2021
-
Planning
-
Design
-
Construction
-
Finish
Q2 2023
The above dates are forecast only and subject to change.
About the project
We expanded the occasional care room and bathroom.
This has made space to offer local children an extra year of funded kindergarten, starting when they are three years old.
The new space is shared by the co-located community centre, and has add seven extra occasional care places.
Funding
In Round 1 of the 2020-2021 Building Blocks Improvement Grant, $282,000 was allocated to this project.
Funding type
Building Blocks Improvement Grant
Reviewed 07 June 2023