School Improvement Fund
-
Start
-
Planning
-
Design
-
Construction
-
Finish
Q4 2016
About the project
We supported various minor works projects at the school through the School Improvement Fund. The school also received a relocatable classroom.
In the 2016–17 State Budget $1.25 million was allocated for a relocatable classroom. In the 2015–16 State Budget, $75,000 was allocated to the school through the School Improvement Fund for minor works at the school.
Permanent Modular School Buildings Program
-
Start
Q2 2019
-
Planning
-
Design
-
Construction
-
Finish
Q1 2020
About the project
The school's new architecturally-designed modular building is now complete. The three-storey building has 12 general purpose classrooms with support spaces and amenities.
The rooms' sliding walls allow for flexible learning spaces and an elevator ensures accessibility for all students. The new building has thermal glazing, low energy lights and water efficient appliances, embracing the school's strong focus on sustainability.
Our modular facilities require less time for planning and construction, resulting in reduced disruption to students, staff and teaching programs. They are sustainable and innovatively designed, with a comparable lifespan to bricks and mortar structures.
The school is benefitting from the Permanent Modular School Buildings Program.
In the 2019–20 State Budget, the school received $6 million.
Reviewed 10 October 2022