Spensley Street Primary School

Location
193 Spensley St Clifton Hill 3068

Upgrade and Modernisation

  • Start

    Q2 2018
  • Planning

  • Design

  • Construction

  • Finish

    Q2 2020

The above dates are forecast only and subject to change.

About the project

We redeveloped and extended the old boiler room into a Science, Technology, Engineering and Maths learning space, and converted the first-floor outdoor terrace into an undercover outdoor area. We also resurfaced the artificial turfed sports area and upgraded the power system.

Funding

In the 2018–19 State Budget $550,000 was allocated to the school. The school also received $330,700 through the School Pride and Sports Funding program.

Funding type

  • Upgrade and Modernisation

Inclusive Schools Fund – Round 8

  • Start

    Q4 2022
  • Planning

  • Design

  • Construction

  • Finish

    Q2 2024

The above dates are forecast only and subject to change.

About the project

We are building an inclusive playground. It will give children of all abilities new ways to socialise, develop and learn through play.

Funding

In Round 8 of the Inclusive Schools Fund, the project received $200,000.
 

Funding type

  • Inclusive Schools Fund

Updated