Non-Government Schools Capital Fund - 2021-22
Start
Q3 2021Planning
Design
Construction
Finish
Q4 2024
The above dates are forecast only and subject to change.
About the project
We are helping the school build the first stage of a new campus. This includes constructing an administration building and a teaching and learning centre comprising 10 general learning areas.
Funding
Under the 2021–22 capital funding program for non-government schools, the school received $5 million.
Funding type
- Non-Government Schools Capital Fund
Updated