Staughton College

Location
Wilson Rd Melton South 3338

Upgrade and Modernisation - more places for local students

  • Start

    Q2 2022
  • Planning

  • Design

  • Construction

  • Finish

    Q3 2025

The above dates are forecast only and subject to change.

About the project

We are modernising and expanding the school. This will give students better learning opportunities and create places for an extra 400 local students. We will replace temporary buildings and build more permanent classrooms.

Funding

In the 2022–23 State Budget, this school received at least $31.77 million.

Funding type

  • Upgrade and Modernisation

Upgrade and Modernisation

  • Start

    Q2 2019
  • Planning

  • Design

  • Construction

  • Finish

    Q3 2021

The above dates are forecast only and subject to change.

About the project

We extended and refurbished the gym and first floor games area. We also transformed old classrooms and facilities into modern learning environments.

Funding

In the 2019–20 State Budget, the school received $650,000. In 2020, the school received $5.85 million.

Funding type

  • Upgrade and Modernisation