Permanent Modular School Buildings Program

  • Start

  • Planning

  • Design

  • Construction

  • Finish

    Q4 2018

The above dates are forecast only and subject to change.

About the project

​We delivered a new architect-designed modular building to the school to replace Block A with a new student library and toilet block.

Funding

In the 2017–18 State Budget, $1,577,000 was allocated to the school.

Funding type

  • Permanent Modular School Buildings Program

Upgrade and Modernisation

  • Start

  • Planning

  • Design

  • Construction

  • Finish

    Q4 2018

The above dates are forecast only and subject to change.

About the project

We have upgraded the school. These works provide the school with contemporary learning spaces that are better suited to modern teaching methods and meeting student needs for the 21st century.​

Funding

In the 2016–17 State Budget Update, $790,000 was allocated to the school. A further $46,000 was allocated in planned maintenance.

Funding type

  • Upgrade and Modernisation

Minor Capital Works Fund - Round 2

  • Start

    Q4 2021
  • Planning

  • Design

  • Construction

  • Finish

    Q3 2023

The above dates are forecast only and subject to change.

About the project

We replaced the perimeter fencing.

Funding

In Round 2 of the Minor Capital Works Fund, the project received $371,868.