Upgrade and Modernisation

  • Start

    Q2 2019
  • Planning

  • Design

  • Construction

  • Finish

    Q2 2023

The above dates are forecast only and subject to change.

About the project

We upgraded and modernised the school to accommodate an extra 200 local students. During Stage 1, we built a specialist learning building for students. In Stage 2, we constructed a three-storey building. It has a multi-purpose hall, music room, and classrooms. We also upgraded the staff administration area and the built a learning resource centre for students.

Funding

In the 2019-20 State Budget, the school received $477,400. In 2020, the school received $15.5 million in funding. The $15.5 million is a share of $130.1 million from the Established Areas Program.

Funding type

  • Upgrade and Modernisation

School Improvement Fund

  • Start

  • Planning

  • Design

  • Construction

  • Finish

The above dates are forecast only and subject to change.

About the project

​We'v​e supported various minor works projects at the school.  ​​ ​

The Victorian Government allocated $10 million to the School Improvement Fund in the 2015-16 State Budget to support minor works projects. 

The School Improvement Fund supports small school projects that contribute to the community's pride in the school, and that help to foster a great relationship between the school and its local community.​​

Funding

In the 2015-16 State Budget, $25,000 was allocated to the school.