Woodend Primary School

Location
146 High St Woodend 3442

Upgrade and Modernisation

  • Start

    Q4 2017
  • Planning

  • Design

  • Construction

  • Finish

    Q1 2019

The above dates are forecast only and subject to change.

About the project

We upgraded the school's music and gym facilities and improved the school grounds. We transformed the school’s multi-purpose hall into a gym with extra storage space. We built a brand new music facility with practice and meeting rooms.

We also landscaped the school grounds. Students can now enjoy an amphitheatre space, refurbished hardcourts, new stairs, decks and ramps.

Funding

In the 2016–17 State Budget, $2 million was allocated to the school. An additional $197,000 funding for maintenance was allocated in 2016.

Funding type

  • Upgrade and Modernisation