Upgrade and Modernisation - Stage 4
-
Start
Q4 2020
-
Planning
-
Design
-
Construction
-
Finish
Q4 2023
About the project
We are delivering the last stage of the school's master plan, which will include the construction of the senior years learning building and additional administration space. This school will benefit from Victoria’s largest ever single investment in upgrading specialist schools, with 39 sharing $388.8 million.
In the 2020-21 State Budget, the school received $8.926 million.
Upgrade and Modernisation - Stage 3
-
Start
Q2 2020
-
Planning
-
Design
-
Construction
-
Finish
Q4 2023
About the project
We are building a middle school building and specialist learning spaces for Yarra Ranges Special Development School. The new facilities include classrooms, a library, TV production studio, digital media, food technology, fitness centre, performance and multiple-purpose room, art room and a variety of supporting amenities.
In 2020, the school received $10 million to deliver the next stage of the masterplan.
Upgrade and Modernisation - Stage 2
-
Start
Q2 2019
-
Planning
-
Design
-
Construction
-
Finish
Q1 2021
About the project
We built a new junior learning building for Yarra Ranges Special Developmental School, and removed an old relocatable building in poor condition. The new junior learning building includes four general purpose classrooms, a laundry, bathrooms, office space, a sick bay and outdoor areas.
In the 2019-20 State Budget, the school received $3.451 million.
Upgrade and Modernisation - Stage 1
-
Start
-
Planning
-
Design
-
Construction
-
Finish
Q4 2019
About the project
We replaced the relocatable administration building with a new administration building. The new building includes a general office, homecrafts café, interview room, staff offices, staff lounge and facilties.
In the 2017-18 State Budget, $500,000 was allocated to the school.
Reviewed 27 January 2022