- 6 Moseley Dr Mount Eliza 3930
Upgrade and Modernisation
Start
Q2 2023Planning
Design
Construction
Finish
Q3 2027
The above dates are forecast only and subject to change.
About the project
Following planning funding, we will upgrade and modernise the school. We are building a double-storey administration building and also refurbishing and extending the main block to create new learning and art facilities. These will give students and staff better learning and work spaces.
Funding
In the 2023–24 State Budget the school shared in $24 million allocated for planning. The 2025-26 State Budget announced total project funding of $11.7 million. This includes earlier planning funding.
Funding type
- Upgrade and Modernisation
Minor Capital Works Fund – 2022–23 State Budget
Start
Q2 2022Planning
Design
Construction
Finish
Q2 2024
The above dates are forecast only and subject to change.
About the project
We refurbished the student toilet block adjacent to main school building, including making plumbing repairs, to improve amenity, cleanliness and hygiene.
Funding
In the 2022-23 State Budget the project received $305,577 from the Minor Capital Works Fund.
Funding type
- Minor Capital Works Fund
Minor Capital Works Fund
Start
Q4 2020Planning
Design
Construction
Finish
Q3 2022
The above dates are forecast only and subject to change.
About the project
We refurbished and modernised a toilet block to improve amenity, cleanliness and hygiene.
Funding
In the 2020 Minor Capital Works Fund the school was allocated $153,165
Funding type
- Minor Capital Works Fund
Updated